Oregon City Home Depot

This is an example of turning a sow’s ear into a silk purse.  Home Depot has agreed to build a store on a site that was considered unusable for regular commercial purposes.  (There is a golf driving range next to this project on the same landfill.)  Construction required the installation of 1100 steel pilings which are visible in some of the pictures.  Reinforced concrete beams were poured on top and integral to the pilings and then the normal (with lots of reinforcing steel bar) slab was poured integral to the concrete beams.  The entire building is on the piling and the infrastructure including water, sewer, fire and storm piping is buried in the usual fashion in the landfill.  The connections from the piping in the landfill which will continue to settle for many years to come are attached to the piping in the building and piping attached to the piling with flexible, extendable ball joints called Flex-Tends® manufactured by EBAA Iron of Eastland, Texas .  The purpose of the Flex-Tends® is to allow the buried piping to pull away from the building as the landfill settles without causing the piping system to fail.  

So far the contractor has used 66 of these units all featuring 3 extension sleeves and 2 balls.  The sizes range from 4” (roof drains) to 24” (main storm sewer line).  The piping system is being installed by Ken Leahy Construction of Hillsboro, Oregon.  The piping materials were supplied by US Filter, Distribution Group, Lake Oswego , Oregon   The piping design was supplied by WRG of Beaverton, Oregon.

 

DSC00001.jpg (186378 bytes) Pressure Test Fixture DSC00002.jpg (60514 bytes) Double 12” Fire Line
DSC00003.jpg (58035 bytes) Double 12” Fire Line w/Restraining Rods for Pressure Test DSC00016.jpg (63676 bytes) Manhole w/18” going in and out the back
DSC00017.jpg (63719 bytes) Manhole w/18” going in and out the back DSC00018.jpg (65420 bytes) Preparing a 16” for installation
DSC00019.jpg (62894 bytes) popping off the plywood end caps DSC00020.jpg (63695 bytes) Lets get those channel locks out
DSC00021.jpg (61072 bytes) gotta do the other end too DSC00022.jpg (63771 bytes) grind surface for cathodic lug installation
DSC00023.jpg (65554 bytes) grind surface for cathodic lug installation DSC1.jpg (67451 bytes)
DSC00025.jpg (61960 bytes) preparing the thermite mixture DSC00026.jpg (64572 bytes) lighting the mixture
DSC00027.jpg (64410 bytes) melted together DSC00028.jpg (65323 bytes) burning the last one
DSC00029.jpg (67315 bytes) lifting the 16” off the crate to install the 16” C-900 nipples DSC00030.jpg (64552 bytes) Who needs AWWA C-600
DSC00031.jpg (64228 bytes) Yep – that’s a torque wrench DSC00032.jpg (65016 bytes) Let’s drop her in the hole
DSC00033.jpg (70246 bytes) Getting closer DSC00037.jpg (63372 bytes) Stab her into the man hole and we are finished